Project Updates

August 2022- Construction on broadband began on August 15, 2022. To verify when service is available in your area go to Connect2First

April 2022 - In design

April 2022 -

  • Elm Street: Arkansas Department of Transportation (ARDOT) 90% complete on design phase. Easements are being determined. Project is scheduled to bidding process in September 2022.

  • Overlays & Street Repairs contract with the Rogers Group has been executed. Notice to proceed will be issued May 20th. For a complete list click the Overlay Project list

  • Dakota Extension Phase I is under construction. Asphalt, permanent striping, and sidewalks have been scheduled. Estimated completion is June 2022

  • N Lincoln Sidewalk Project in process with design team.

  • Locust Street Project in process with design team.

  • St. John Street, 10th Street, Belair Circle, Belair Cove, Century Circle Project in process with design team.

April 2022 -

  • Barnwell Drainage Project 90% complete on design phase. Project is scheduled to bidding process in June 2022.

  • Shiloh Drainage Project in process with design team.

  • Crestwood Drainage Project in process with design team.


August 2022

  • Police and Fire Training Facility in process with design team. Location has been determined, and project cost analysis is being assessed.

  • Due to supply delays Body and Dash cameras are expected to be delivered by December 2022.

  • Due to supply delays Portable radio devices are expected to be delivered by January 2023.

April 2022 -

  • Police and Fire Training Facility in process with design team. Location has been determined, and project cost analysis is being assessed.

  • Body and Dash cameras have been ordered. Expected delivery is July 2022

  • Portable radio devices have been ordered. Expected delivery is June 2022

August 2022

  • Police and Fire Training Facility in process with design team. Location has been determined, and project cost analysis is being assessed.

April 2022 -

  • Police and Fire Training Facility in process with design team. Location has been determined, and project cost analysis is being assessed.

  • Heavy Rescue vehicle has been ordered and is in currently in production. Estimated delivery is April 2023

August 2022- All sirens have been installed and are fully functioning.

April 2022 - All sirens have placed in the City. Currently 6 sirens are active and operational. The additional 6 sirens are waiting for electrical requirements.

August 2022- Architectural plans 100% complete. Project will go out to bid in August 2022, and results will be awarded in October 2022. Projected start date on facility is January 2023

April 2022 - Architectural plans 30% complete. Expect 60% in June. Project is scheduled to start and bidding process in September 2022.

August 2022- Cabot Sports Complex

  • architectural plans 90% completed. Expect 100% by September.

  • Project will go out to bid in October 2022, and results will be awarded in November 2022

  • Projected start date on facility is February 2023

Wave pool project will go to bid in August 2022

Splash Pad location has been determined, and project cost analysis is being assessed.

Inclusive Playground package has been purchased and delivered. Location has been determined. Projected start date is September 2022


April 2022 - Cabot Sports Complex

                • architectural plans 30% completed. Expect 60% in May.

                • Project is scheduled to start and bidding process in August 2022.

                • Construction Management RFQ advertised. Review of applications packets May 3, 2022. Anticipate that Construction Management firms will be under contract by June 2022. Cost analysis will be completed at that time.

Splash Pad and Inclusive Playground package has been ordered. Estimated delivery is October 2022

Wave pool project is scheduled to start construction August 2022. Estimated completion is May 2023

January 2022 - Baseball field turf project completed


Public Health Facilities & Improvements

August 2022- Architectural plans 100% complete. Project will go out to bid in August 2022, and results will be awarded in October 2022. Projected start date on facility is January 2023

April 2022 - Architectural plans 30% complete. Expect 60% in June. Project is scheduled to start and bidding process in September 2022.