April 2022 - In design

April 2022 -

  • Elm Street: Arkansas Department of Transportation (ARDOT) 90% complete on design phase. Easements are being determined. Project is scheduled to bidding process in September 2022.

  • Overlays & Street Repairs contract with the Rogers Group has been executed. Notice to proceed will be issued May 20th. For a complete list click the Overlay Project list

  • Dakota Extension Phase I is under construction. Asphalt, permanent striping, and sidewalks have been scheduled. Estimated completion is June 2022

  • N Lincoln Sidewalk Project in process with design team.

  • Locust Street Project in process with design team.

  • St. John Street, 10th Street, Belair Circle, Belair Cove, Century Circle Project in process with design team.

April 2022 -

  • Barnwell Drainage Project 90% complete on design phase. Project is scheduled to bidding process in June 2022.

  • Shiloh Drainage Project in process with design team.

  • Crestwood Drainage Project in process with design team.


April 2022 -

  • Police and Fire Training Facility in process with design team. Location has been determined, and project cost analysis is being assessed.

  • Body and Dash cameras have been ordered. Expected delivery is July 2022

  • Portable radio devices have been ordered. Expected delivery is June 2022

April 2022 -

  • Police and Fire Training Facility in process with design team. Location has been determined, and project cost analysis is being assessed. .

  • Heavy Rescue vehicle has been ordered and is in currently in production. Estimated delivery is April 2023

April 2022 - All sirens have placed in the City. Currently 6 sirens are active and operational. The additional 6 sirens are waiting for electrical requirements.

April 2022 - Architectural plans 30% complete. Expect 60% in June. Project is scheduled to start and bidding process in September 2022.

April 2022 - Cabot Sports Complex

                • architectural plans 30% completed. Expect 60% in May.

                • Project is scheduled to start and bidding process in August 2022.

                • Construction Management RFQ advertised. Review of applications packets May 3, 2022. Anticipate that Construction Management firms will be under contract by June 2022. Cost analysis will be completed at that time.

Splash Pad and Inclusive Playground package has been ordered. Estimated delivery is October 2022

Wave pool project is scheduled to start construction August 2022. Estimated completion is May 2023

January 2022 - Baseball field turf project completed


Public Health Facilities & Improvements

April 2022 - Architectural plans 30% complete. Expect 60% in June. Project is scheduled to start and bidding process in September 2022.